PROJECT MANAGEMENT PROCESSES
1. What is a project process?
Please Select
A. The creation of a product or service
B. The progressive elaboration resulting in a product
C. A series of actions that bring about a result
D. A series of actions that allow the project to move from concept to deliverable
2. Within a project there are two distinct types of processes. Which of the following processes is unique to the project?
Please Select
A. EVM processes
B. Project management planning
C. IPECC
D. A product-oriented process
3. There are five project management processes that allow projects to move from start to completion. Which one of the following is not one of the project management process groups?
Please Select
A. Initiating
B. Planning
C. Communicating
D. Closing
4. Of the following, which is the logical order of the project management processes?
Please Select
A. Initiating, planning, controlling,B executing, closing
B. Planning, initiating, controlling, executing, closing
C. Initiating, planning, executing, controlling, closing
D. Planning, initiating, executing, closing
5. Which of the project management processes is progressively elaborated?
Please Select
A. Planning
B. Communicating
C. Contract administration
D. Closing
6. The ongoing process of project planning is also known as ____________________.
Please Select
A. Constant integration planning
B. Rolling wave planning
C. Continuous planning
D. Phase gates
7 The information from the planning phase is input into which of the following processes?
Please Select
A. Initiating
B. Controlling
C. Executing
D. Closing
8. The information from the initiating phase is input into which of the following processes?
Please Select
A. A. Planning
B. Executing
C. Controlling
D. All of the project phases
9. Which process represents an ongoing effort throughout the project?
Please Select
A. Lessons learned
B. Planning
C. Closing
D. EVM
10. Which of the following planning processes is concerned with reporting relationships?
Please Select
A. Organizational planning
B. Resource planning
C. Scope planning
D. Activity definition